22 Nov 2019

Completion of the asphalt paving works on Patras Bypass

Further to the asphalt paving works that were carried out on Patras Bypass in the previous days, follows a third phase for the installation of shaft covers at their final position; such phase will require traffic arrangements and short night closures.

In particular, on the section from K1 Patras I/C (k.p. 205,150) to Eglykada I/C (k.p. 212,600) from Monday 25/11 to Wednesday 18/12 the traffic at the zone of works will alternatively use the right and the emergency lanes or the left lane.

In particular, to perform the works for securing the worksite in the area of the tunnels, short night traffic closures will be implemented in the direction to Athens, according to the following time schedule:

 

Start time - date

End time - date

21:00 - Monday 25/11/2019

06:00 - Tuesday 26/11/2019

21:00 - Tuesday 03/12/2019

06:00 - Wednesday 04/12/2019

21:00 - Sunday 08/12/2019

06:00 - Monday 09/12/2019

21:00 - Sunday 15/12/2019

06:00 - Monday 16/12/2019

21:00 - Tuesday  17/12/2019

06:00 - Wednesday 18/12/2019

 

 

During the above traffic arrangements, the traffic to Athens will use the following streets: Eleftheriou Venizelou, Akti Dimeon, Trion Navarchon, Agiou Andrea, Norman, Iroon Politechniou and Kanelopoulou and will re-enter the Korinthos-Patras NNR at Patras K1 I/C.

For the relevant works in the direction to Pyrgos, to be implemented after the Christmas holidays, a newer announcement will be issued. 

Olympia Odos would like to thank the drivers for their understanding and invites them to comply with the relevant signage and the instructions of the Traffic Police, as well as to be particularly careful when crossing the said areas.

share: