Construction of a roundabout at the intersection of Megara Interchange with the O.N.R.

Within the context of the infrastructure heavy maintenance works on the motorway, existing structures – Underpasses are reconstructed. Specifically, in the area of Megara Interchange (k.p. 38.7) a new roundabout will be constructed at the intersection of the exit ramp of the motorway with the Athens - Korinthos Old National Road (O.N.R.), for the improvement of the level of service and the safety of local users.  

To implement works, a short-term closure of the exit ramp of the motorway, from Athens to Megara will be applied from Thursday morning, February 11, at 07:00 a.m., until not later than Thursday night, February 18, at 21:00 p.m.

During this period of time, the traffic will use the Athens-Korinthos O.N.R. with the local road network as well as N. Peramos & Pachi Interchanges (k.p. 33.4 & 41.0) as shown at the diagam. The entrance ramp in the direction to Athens will remain open.

Olympia Odos would like to thank the drivers for their understanding and invites them to comply with the relevant worksite signage and the instructions of the Traffic Police, as well as to be particularly careful when crossing the said areas.